Rick Heistinger, the manager of the HyTek Construction parking lot job, would like residents to be aware of their following schedule for this week Nov 20-25:

Our wish list for this week is as follows.
Monday, may open up another small section of street for culvert, but will not be closing road...this may not happen til Tues, wed or Thurs...fall back scope of work not priority.
Wednesday Morning, pouring middle wall section concrete.
Thursday Morning, Pouring east end foundation.
Friday Morning, Pouring west end walls.
This is approx, and numerous variables may change current plans plus or minus a day.
Thanks for your help and cooperation to all residence in area, we're on the home stretch now.
Rick